WIP  ·  Cost to Cost  ·  Free Calculator

Construction Work in Progress and Percentage of Completion Calculator

Build a defensible WIP schedule for the bank, the bonding company and the T2. Work out percentage complete, revenue to recognise, over and under billings, and any loss you must accrue in full today.

Percentage complete
Revenue to recognise
Over and under billings
Loss jobs accrued

Job 1

Approved change orders only


Actual cost on the job


The estimate that drives everything


Including amounts held as holdback


Usually 10% under the Construction Act


For the schedule

Job 2

Enter zero if not applicable


Actual cost on the job


Above contract value means a loss


Including holdback


Sitting in receivables


For the schedule

Job 3 and the Corporation

Enter zero if not applicable





Money you are holding back from others


On these same jobs

Year-End Position
—
—

—
revenue to recognise

Revenue Earned to Date

—

Underbillings

—

Overbillings

—

Gross Profit to Date

—

WIP Schedule by Job

JobContract% CompleteRevenue EarnedBilledOver / (Under)Gross Profit

Balance Sheet Presentation

ItemWhere It GoesAmount

Jobs Needing Attention

JobIssueAction

Points That Decide This

    What to Do Next

    —

    Disclaimer: This calculator applies the cost-to-cost method of measuring progress, under which percentage complete is costs incurred to date divided by total estimated costs at completion, and revenue earned to date is that percentage applied to the contract value including approved change orders. Other measures of progress may be more appropriate for particular contracts. Under Canadian accounting standards for private enterprises, revenue from a contract may be recognised using the percentage of completion method where the outcome can be reasonably estimated and performance consists of the execution of more than one act, and the completed contract method may be appropriate in defined circumstances; the choice of policy and its application should be determined with reference to the applicable standard and the entity’s circumstances. Where total estimated costs exceed the contract value, the entire expected loss is generally recognised immediately rather than spread across the remaining term. Amounts billed in excess of revenue earned are presented as a liability and amounts earned in excess of billings as an asset, and holdback receivable is generally presented separately. Unapproved change orders and claims are subject to specific recognition criteria and have been excluded here; only approved change orders should be included in contract value. For income tax purposes, a professional or other election and specific provisions may affect the timing of income inclusion, and the accounting treatment does not automatically determine the tax treatment. Holdback amounts under the Construction Act (Ontario) have their own statutory rules regarding retention and release which are addressed separately. Figures produced here are indicative planning estimates and are not a substitute for prepared financial statements or a filed return. This page is general information, not accounting or tax advice.

    The Cost Estimate Is the Whole Schedule

    Cost to cost is arithmetic. Costs incurred divided by total estimated costs gives percentage complete, and that percentage applied to the contract value gives revenue earned.

    Everything therefore rests on one number that nobody can verify from outside: the total estimated cost at completion. Get that wrong and every figure below it is wrong, in the same direction, on every job.

    Understating estimated costs overstates both percentage complete and profit. It is the single most common problem in construction financial statements, and it is rarely deliberate. It is usually a project manager being optimistic about a job that is quietly going sideways.

    Loss Jobs Are Recognised in Full, Immediately

    This is the rule that catches contractors out at year end. Where total estimated costs exceed the contract value, the entire expected loss goes into the accounts now. Not spread over the remaining months. All of it, today.

    A job forty percent complete with a hundred thousand dollar projected loss takes the full hundred thousand this year. There is no matching it to future progress.

    That rule is also why the estimate matters so much. A job that is marginally profitable on paper and genuinely loss-making in reality is hiding a full loss accrual that will surface eventually, usually at the worst moment for the bank covenant.

    Overbillings and Underbillings Tell Two Different Stories

    These are the numbers a lender reads first, and they mean opposite things.

    What It IsWhat It Signals
    OverbillingsBilled more than earnedGood cash flow, or a job billed ahead
    UnderbillingsEarned more than billedWork done and not invoiced

    Overbillings are a liability. You are holding customer money for work not yet done, which funds the business but is not profit. Underbillings are an asset and usually a problem, because unbilled work is work you have paid for and not been paid for.

    Large underbillings are the classic warning sign. Either the billing process has fallen behind, or there is a dispute nobody has mentioned, or costs are running over and the schedule has not caught up. All three are worth knowing before the bank asks.

    Only Approved Change Orders Belong in Contract Value

    Contract value should include approved change orders and nothing else. Unapproved change orders and claims have their own recognition criteria and are frequently the difference between a job that looks profitable and one that is.

    A contractor who has done a hundred thousand dollars of extra work on a verbal instruction has real exposure. Putting it in the contract value because everyone agrees it will be approved is exactly how a WIP schedule stops being defensible.

    Holdback Sits on Both Sides

    You have holdback billed to customers and not yet received, and holdback you are retaining from your own subcontractors. Both need to be visible.

    The customer holdback is a receivable and generally presented separately, because a lender wants to see how much of your receivables cannot be collected yet by law. The subcontractor holdback is a payable, and it is real money going out when the lien periods expire.

    What the Bank and the Bonding Company Look For

    1. A job-by-job schedule, not a single aggregated number
    2. Consistent estimating, with a track record of estimates that held
    3. Underbillings explained, since they are always the first question
    4. Loss jobs disclosed, accrued in full, with an explanation
    5. Holdback separated on both sides of the balance sheet
    6. Change orders that are approved rather than expected

    Bonding capacity turns on the reliability of your numbers as much as their size. A contractor whose estimates have been accurate for three years gets more capacity than one with better margins and a history of revisions.

    Accounting and Tax Are Not the Same Question

    How revenue is recognised for financial statement purposes and how income is included for tax are related but distinct. The accounting treatment does not automatically settle the tax treatment.

    Where the two diverge, the difference belongs in the T2 reconciliation rather than in the WIP schedule. Worth having someone who does both look at it, because a contractor optimising one in isolation usually creates a problem in the other.

    What This Calculator Does Not Cover

    • Whether percentage of completion is the right policy for your contracts
    • Unapproved change orders and claims, which have their own criteria
    • The full T2 reconciliation between accounting and tax
    • Holdback release timing under the Construction Act
    • Joint ventures and partnership interests
    • More than three jobs, which needs a proper schedule

    Build the schedule before the year end, not after. Our construction accounting service covers the WIP schedule, the statements and the T2.

    Frequently Asked Questions

    Common questions on construction WIP.

    How do I calculate percentage complete?
    Under the cost-to-cost method it is costs incurred to date divided by total estimated costs at completion. That percentage applied to the contract value including approved change orders gives revenue earned to date.

    What happens if a job is going to lose money?
    The entire expected loss is generally recognised immediately rather than spread over the remaining term. A job 40% complete with a $100,000 projected loss takes the full $100,000 this year, which is the rule that catches contractors out at year end.

    What are overbillings and underbillings?
    Overbillings are amounts billed in excess of revenue earned, presented as a liability because you hold customer money for work not yet done. Underbillings are revenue earned in excess of billings, presented as an asset and usually signalling a problem.

    Why are large underbillings a warning sign?
    Because unbilled work is work you have paid for and not been paid for. It usually means billing has fallen behind, there is an unmentioned dispute, or costs are running over and the schedule has not caught up. The bank will ask about it first.

    Should unapproved change orders go in the contract value?
    No. Only approved change orders belong there. Unapproved change orders and claims have their own recognition criteria, and including expected approvals is exactly how a WIP schedule stops being defensible to a lender or an auditor.

    How should holdback be presented?
    Customer holdback is a receivable and is generally shown separately, because a lender wants to see how much of your receivables cannot legally be collected yet. Subcontractor holdback you retain is a payable and represents real cash leaving when lien periods expire.

    What do bonding companies actually assess?
    The reliability of your numbers as much as their size. A contractor whose cost estimates have proven accurate over three years generally gets more capacity than one with better margins and a history of revisions.

    Is the accounting treatment the same as the tax treatment?
    They are related but distinct, and the accounting policy does not automatically settle the tax position. Where they diverge the difference belongs in the T2 reconciliation, which is why both should be looked at together.

    Get the Schedule Right Before Year End

    Send us your job list with costs, estimates and billings. We will build the WIP schedule, flag the loss jobs and the underbillings, and prepare statements the bank and the bonding company will accept.